| Performance Measure | Priority Area | Title | Agency | Who | Forum Date | Status | Due Date |
| 1.1 - Rate of Violent Infractions | Public Safety | Implement Violence Reduction Initiative | DOC | Richard Morgan, Assistant Secretary for Prisons | 2009-04-15 | Completed | 12/31/2008 |
| 1.3 - Participation in Prison Reentry Programs | Public Safety | Set FY 2009 Prison Reentry Targets | DOC | Anmarie Aylward, Offender Programs Administrator | 2008-09-19 | Completed | 12/31/2008 |
| 1.3 - Participation in Prison Reentry Programs | Public Safety | Prison Reentry Program Development and Delivery | DOC | Anmarie Aylward, Offender Programs Administrator | 2008-09-19 | Completed | 7/31/2009 |
| 2.2 - Timely Intake Process | Public Safety | Timely Intakes | DOC | Karen Daniels, Assistant Secretary | | Completed | 9/15/2009 |
| 2.3 - Participation in Community Reentry Programs | Public Safety | Set FY 2009 Community Reentry Targets | DOC | Mary Leftridge Byrd, Assistant Secretary for Offender Programs | 2008-09-19 | Completed | 12/31/2008 |
| 2.3 - Participation in Community Reentry Programs | Public Safety | Community Reentry Program Development and Delivery | DOC | Mary Leftridge Byrd, Assistant Secretary for Offender Programs | 2008-09-19 | Completed | 12/31/2008 |
| 2.3 - Participation in Community Reentry Programs | | Revise reentry targets based on 2009-11 budget | | Anmarie Aylward | | Completed | 7/31/2009 |
| 2.3 - Participation in Community Reentry Programs | Public Safety | Establish Measure on Percentage of Need | DOC | Dave Daniels, Director-Planning and Research | | Not Started | |
| 2.4 - Percent of On Time Violation Hearings in the Community | Public Safety | Complete 90 Day First Appearance Pilot | DOC | Scott Blonien, Assistant Secretary for Regulatory Compliance | 2008-09-19 | Completed | 5/31/2009 |
| 2.5 - Percent Attainment of Offender Reentry Needs | Public Safety | Implement Performance Measures | DOC | Karen Daniels, Assistant Secretary for Community Corrections | | Completed | 3/31/2009 |
| 3.1 - Statewide Response-Level Communications | | Develop statewide protocols and procedures | | WSP | 2010-06-16 | In Progress | 6/1/2011 |
| 3.1 - Statewide Response-Level Communications | Public Safety | Statewide Communications Interoperability Plan (SCIP) | WSP | WSP | 2010-06-16 | In Progress | 3/31/2011 |
| 3.1 - Statewide Response-Level Communications | Public Safety | Computer Asset Survey Mapping | WSP | WSP | 2010-06-16 | In Progress | 10/31/2011 |
| 3.1 - Statewide Response-Level Communications | Public Safety | National Emergency Communications Plan (NECP) | WSP | WSP | 2010-06-16 | In Progress | 10/31/2011 |
| 3.1 - Statewide Response-Level Communications | Public Safety | Cross-Border Programming Agreements | | WSP | 2010-06-16 | In Progress | 2/1/2011 |
| 3.2 - Students Trained by the Fire Training Academy | Public Safety | Partner with Canadian Fire Fighters | WSP | WSP/Vancouver BC Fire Departments | | In Progress | 3/1/2012 |
| 3.2 - Students Trained by the Fire Training Academy | Public Safety | Operation Support | WSP | WSP State Fire Marshall's Office | | Not Started | 12/1/2012 |
| 3.2 - Students Trained by the Fire Training Academy | Public Safety | New Burn Building (pre-design) | WSP | GA/WSP | | In Progress | 12/12/2011 |
| 3.2 - Students Trained by the Fire Training Academy | Public Safety | Master Plan - New Burn Building | WSP | WSP | | Not Started | 12/2/2013 |
| 3.3 - Next Generation 911 | | Phase 1 - ESInet Proof of Concept | | D. Irwin, EMD | | Completed | 5/15/2010 |
| 3.3 - Next Generation 911 | | Phase 2 Database conversions | | J. Randall, EMD | | Completed | 1/15/2010 |
| 3.3 - Next Generation 911 | | Phase 2 ESInet connections to remaining PSAPS, 31 counties including testing. | | J. Randall, EMD | | In Progress | 3/14/2012 |
| 3.3 - Next Generation 911 | | Phase 3 - Equipment consolidation execution strategy | | E911 Advisory Committee | | In Progress | 11/30/2011 |
| 3.3 - Next Generation 911 | | Phase 3 - Pilot project to validate PSAP equipment centralization. | | J. Randall, EMD | | Not Started | 6/30/2012 |
| 3.3 - Next Generation 911 | | Phase 3 - Equipment centralization and digital upgrade statewide | | J. Randall, EMD | | Not Started | 6/30/2016 |
| 3.3 - Next Generation 911 | | Phase 3 - Telephone company end office re-homing | | J. Randall, EMD | | Not Started | 12/31/2013 |
| 3.3 - Next Generation 911 | | Phase 3 - Full NG911 implementation statewide | | J. Randall, EMD | | Not Started | 6/30/2017 |
| 4.1 - Workplace Fatalities | Public Safety | Agriculture Industry Focus on Tractor Rollover | L&I | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.1 - Workplace Fatalities | Public Safety | Fatality Education and Outreach | L&I | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.1 - Workplace Fatalities | | Construction Industry Focus on Safety | | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.2 - Workplace Injury and Illness Rates | Public Safety | WISHA Advisory Committee | | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.2 - Workplace Injury and Illness Rates | Public Safety | Integrated Models for Risk Management | | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.2 - Workplace Injury and Illness Rates | Public Safety | SHIP Grant Support | | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.2 - Workplace Injury and Illness Rates | | Abatement Legislation | | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.2 - Workplace Injury and Illness Rates | | WISHA Penalty Policy | | Michael Silverstein | 2010-06-16 | In Progress | |
| 4.3 - Hazards Identified and Fixed | | Scheduling Workplace Visits | | Michael Silverstein | | In Progress | |
| 4.3 - Hazards Identified and Fixed | | Hazard Surveillance System | | Michael Silverstein | | In Progress | |